旋转补偿器

NEWS

Contact us

Jiangsu Yuyang mechanical equipment Co., Ltd.

Address: Louzhuang industrial area of Jiangyan District, Taizhou, Jiangsu

Contact: Mr. Chen

Mobile phone: 18952657999 13801420111

Tel: 052388800188

Fax: 052388865288

Zip code: 225506

Mailbox: jiangsuyuyang008@163.com

Web site: www.jsyyjx.com.cn

Shanghai Yuyang machinery and equipment Technology Co., Ltd.

Address: Shanghai city Hongkou District Zhoujiazui Road No. 991

Contact: manager Chen

Cell phone: 18601780966

Zip code: 200086

Tel: 02165875265

Web site: www.jsyyjx.com.cn


Detailed explanation of the installation process of spherical compensator

Your current position: HOME >> News >> Industry dynamics

Detailed explanation of the installation process of spherical compensator

Release date:2017-12-28 Author:www.jsyyjx.com.cn Click:

Compensator installation general process

1. scope of application.

This process is suitable for installation of gas pipeline, heat pipe and industrial pipe compensator.

2. reference the standard.

SY0401 - 98S "code for construction and acceptance of line engineering for oil and gas pipeline project"

CJJ28 - 2004 code for construction and acceptance of urban heating pipe network engineering

GB50235 - 97 code for construction and acceptance of industrial metal pipeline engineering

  

球形补偿器

Inspection of 3. compensator before installation

Before the installation of the compensator, the following items must be inspected:

3.1 whether the compensator used is in conformity with the state's current relevant standards.

3.2 whether the supplier has the manufacturing license for the pressure pipe element.

3.3 the quality certificate of the supplier shall not be lower than the current relevant standards.

3.4 appearance inspection, no cracks, slag, folding, over burning and other defects, no more than the wall thickness negative deviation pit.

3.5 the inspection of geometry size, the length of installation should conform to the design requirements.

Preparation of 4. compensator before installation

4.1 the pre deformation compensator is needed, the pre deformation quantity should conform to the design requirements and the pre deformation amount should be recorded.

4.2 the pretension (compression) of the pipes must conform to the design requirements, and the following conditions should be provided before the pretension:

All welds (except pretension) in the 4.2.1 prestretched area are welded (except for pretension), and the heat treated weld is required to be inspected after heat treatment.

Support 4.2.2 stretching region is installed, the pipe and the fixed bracket is properly fixed hanger pre tension near the mouth of the reserved enough adjustment margin, the hanger spring has, according to the design requirements and the temporary fixed compression load, the spring bearing pipe.

All connection bolts in 4.2.3 pretension area have been fixed.

Installation of 5. compensator

5.1 "M" or "" installation of the compensator.

5.1.1 in the piping or weld layout should pay attention to, because of the bending stress of the flat arm is the largest, so the weld should not be placed in the central part of the flat arm, the weld layout of cantilever in the square compensator (or vertical arm) in the middle as well, because this part of the minimum bending stress.

5.1.2 according to the design document pre tension (or compression), the pre tension (or compression) volume should meet the design requirements, installation deviation less than 10mm.

When 5.1.3 is installed, the parallel arm should be the same as the pipeline slope, and the two vertical arm should be horizontal.

5.1.4 if plumbing is installed, the exhaust and drainage device should be set up.

The pre offset of the pulley at the 5.1.5 compensator should be in accordance with the design requirements.

The installation of 5.2. filling compensator.

The 5.2.1 is checked with the design pattern, and there is at least one guide bearing on both sides of the filler compensator.

When 5.2.2 is in place, it is noted that the compensator and the pipe must remain concentric (shaft) and must not be skewed.

5.2.3 should change the installation length and temperature as specified in the design document, leaving the remaining shrinkage.

The residual shrinkage value of the unidirectional filling compensator is calculated by the press formula, and its allowable deviation is + 5mm.

S=SO

In the form of S - the installation of residual contraction (mm) between the casing pipe and the enclosure ring

The maximum stroke of the S0 compensator (mm)

T0--- outdoor minimum design temperature (centigrade)

Temperature (c) at installation of t1-------- compensator

The highest design temperature (c) of t2--- medium (c)

5.2.4 adopts the packing compensator with molded packing ring. The varieties and specifications of the packing shall be in conformity with the regulations. The interface of the packing ring should be made into an inclined plane with a cylindrical axis of 45 degrees to fill the packing ring. The packing shall be loaded by turns and compressed by one cycle, and the interfaces of each ring shall be staggered. Use the non - molding filler compensator, filling and filling sealing packing in order pressure in order according to the specified pressure.

5.2.5 intubation should be installed at the inflow end of the medium

The 5.2.6 guide bracket should be set on the side of the tube to ensure free expansion and no deviation from the center.

Installation of 5.3 wave compensator

5.3..1 installed with general waveform compensator according to the provision of design documents pre tensioning or preloading, the tensile or compression method, the compensator is connected with one end of the fixed in the pipeline, and then the waveform compensator tension or compression to the thermal elongation of 1/2 cable, and then immediately and the other end of the pipe are connected and fixed. The deviation should not exceed the pre tension (or compression) amount of 5mm. Pre stretching (or compression) can also be carried out on the flat ground, and the force should be increased gradually by 2~3 times, so as to ensure uniform stress on the circumferential surface of each wave joint. When a temporary restraining device is set up when the required value is reached, it can be fixed and fixed. When the design document is not specified, the amount of tension or compression of the installation waveform compensator can be selected according to Appendix 3.

When 5.3.2 is in place, it should be noted that the inner sleeve has one end of the weld, and the direction of the medium flows to the horizontal pipe, which should be placed on the upper part of the plumbing pipe.

When 5.3.3 is in place, it should be kept in line with the pipe (heart).

5.3.4 is strictly forbidden to use the compensator to install the adjustment in the adjusting pipe so as to avoid the normal function of the compensator.

When the 5.3.5 is fixed to the pipe, the temporary restraints can be dismantled and the limiting device can be adjusted to the specified position. After the temporary support is dismantled, the compensator is only allowed to bear axial force and can not be subjected to lateral force.

Installation of 5.4 ball type compensator

The 5.4.1 spherical compensator should prevent the collision during loading and unloading, when the sphere is kept clean.

5.4.2 ball compensator before installation, should be adjusted to the required angle sphere, and from the pipe combined with the center.

5.4.3 ball compensation should be installed close to the elbow, the sphere center distance length is greater than the calculated length.

The direction of installation of 5.4.4 ball type compensation should be correct. The medium should be inflow from the end of the sphere and outflow from the end of the shell.

5.4.5 when the ball type compensator is installed vertically, the end of the shell shall be above.

The fixed support or sliding support of 5.4.6 spherical compensation must be constructed according to the design rules.

6. notices in the installation process of the compensator:

Attention should be paid to the installation of compensator:

6.1 before installation, each compensable model and installation position must be checked according to the design pattern.

6.2 compensators should have temporary restraints and reliable reinforcement measures before they are hoisted to the position.

6.3 compensator hoisting in place


Related tags:四氟补偿器

Recently browse:

share
Welcome to our message
Please enter the message content, we will contact you as soon as possible。
Full name
Full name
Telephone
Telephone
mailbox
mailbox
address
address